Expansion Delay: Solutions
Director of Planning hired
Development ramped up significantly
- Proven reserves to increase to 3 mm tons (+1.2 mm)
- Development increased to 83,000 ft vs. 45,000 ft
- Diamond drilling increased to 588,000 ft vs. 324,000 ft
Bottlenecks being addressed
- Ore/waste movement
- Equipment availability
- Mine infrastructure
- Backfill systems