Optimiz Program Update
Goals Status
51 DCs to 30 13 Consolidations Completed (to 38)
3 Consolidations in FY04
Build 6 New DCs 4 New DCs Under Construction
First One Opens Summer of ‘04
Expand 7 DCs 2 Completed
1 Expansion in ‘04
On Schedule, On Budget!
Substantial Synergy Opportunity
?