|
Renovation:
The purpose of the Renovation phase is to ensure all date routines
have been corrected to properly address Year 2000 dates. During
1999 the Corporation completed 100% of the renovation for all “in-house”
applications (both “mission critical” and non-“mission critical”).
Installation of vendor supplied upgrades were also completed during
1999 for the other “mission critical” and non-“mission critical”
applications.
Validation:
The Validation phase consists of various types of testing and
retesting. FirstMerit performed extensive testing of both in-house
and vendor written systems as well as the various connections to
other systems (internal and external). Non-information system applications
or functions such as vault operations and security systems were
also tested. Testing guidelines were issued to ensure consistency
and completeness throughout the organization. Integrated testing
was completed to ensure the applications worked together. During
1999, major integrated tests occurred in March, May and October.
For example, in excess of 100 applications were successfully tested
on May 18-19, 1999. “Future dates” (i.e., the system’s ability to
properly recognize dates involving the Year 2000 and beyond) were
tested for both “mission critical” and non-”mission critical” systems.
Implementation:
During the Implementation phase, systems are certified as Year
2000 compliant and placed into production. FirstMerit placed systems,
once renovated and validated, into production throughout the project.
Another FFIEC
area mentioned was contingency planning. FirstMerit enhanced current
contingency plans throughout the organization with specific Year
2000-caused problem scenarios. Business areas reviewed departmental
Year 2000 risks and incorporated changes to their contingency plans.
This process was completed by June 30, 1999.
FirstMerit
successfully opened 43 branches on January 1, 2000. No significant
Year 2000 issues have been identified as of the date of publication
of this Annual Report. Efforts expended during the life of the project
helped ensure a smooth transition into the 21st century.
The Corporation’s
total Year 2000 readiness project costs spent project life to date
(including the estimated costs and time associated with the impact
of a third party vendor’s Year 2000 issues) are based on presently
available information. There can be no guarantees, however, that
the systems and applications of other companies on which the Corporation’s
systems and applications rely are completely Year 2000 trouble free,
and therefore, will not have material adverse effect on the Corporation.
The total operating
costs of the Year 2000 readiness project are estimated at $6.1 million.
The costs incurred to date have been funded through operating cash
flows and have not had a material adverse effect on the Corporation’s
results of operations. Included in the $6.1 million estimate of
total project costs are capitalized amounts of approximately $1.0
million. During 2000, the Corporation expects to incur the last
of the project costs (included in the $6.1 million estimate) of
approximately $530,000, related mostly to project related incentives.
|