Duratek
is a member of the Fluor Fernald team that is managing decommissioning
of the former uranium processing facility at the U.S. Department
of Energy’s (DOE) Fernald Closure Project (FCP) in southern
Ohio. Part of the decommissioning effort requires stabilization
and disposal of approximately 8,900 cubic yards of low-level,
radium-bearing waste presently stored in Silos 1 and 2. Duratek’s
role in this important project includes (a) providing the
process technology, (b) designing and testing waste packages,
and (c) testing and improving the design of the full-scale
prototype remote handling loading facility to ensure operability
and maintainability. This article examines one aspect of the
project: package design and testing.
The waste stored in the silos is a by-product of processing
uranium ores and will be stabilized by mixing it with cement
and fly ash in a treatment facility presently being constructed
on the FCP site. Once stabilized, the waste will be transported
in custom-designed packages for disposal beginning in November
2004 and ending in approximately December 2005. Waste from
the silos project will fill approximately 7,000 packages.
Duratek designed the waste packages to meet both federal
transport regulations and waste acceptance criteria, so repackaging
is not necessary once it reaches the disposal site, saving
DOE time and money. Each package is approximately six and
one-half feet tall and six feet in diameter and weighs slightly
less than 22,000 pounds when filled. For transportation purposes,
the containers were designed as Industrial Packaging Type
2 (IP-2). By definition, this means the containers meet strict
regulatory safety standards such as shielding, containment,
and structural strength. Package testing was performed to
verify compliance with regulatory and project requirements.
Leak Testing: A series of tests were performed to
assess the sealing capability of possible lid closure joint
configurations. This testing verified sufficient leak tightness
through the lid seal could be achieved, and determined the
number of rivets needed to seal the lid. A tight seal is required
to prevent possible release of radon from the container.
Drop Testing: Prototype Silos 1 & 2 packages were
fabricated and filled with concrete for drop testing as required
for IP-2 packages. Three sets of drop tests were conducted,
the first two being preliminary assessments prior to the record
tests. These preliminary tests were conducted from a height
of four feet. The record drop tests of the prototype packages
were conducted by the National Transportation Research Center
located near Oak Ridge, Tennessee. Three drop orientations
from a height of three feet were performed: top end, side,
and center of gravity over corner.
Stacking Test: A stacking test was conducted on one
of the prototype packages, as also required of IP-2 packages.
This consisted of placing a compressive load of 109,750 pounds
on the package, based on five times the maximum weight of
a package, for 24 hours.
The method designed for loading packages onto the trailer
at the FCP Treatment Facility and unloading them at the disposal
site, and for installing and removing the tiedown system,
was intended to support the shipping schedule while minimizing
personnel exposure when working close to the packages. Duratek
fabricated a prototype of the trailer and tiedown system to
ensure design features worked as intended. The prototype trailer
and tiedowns were tested using the prototype containers for
functionality and total vehicular weight. Besides performing
many tests loading and unloading packages, Duratek transported
the trailer and two prototype packages from South Carolina
to the FCP in Ohio, and back.
After an intense, two-year effort on the Silos 1 and 2 transportation
equipment, design of all the necessary equipment is finalized,
the prototypes have been fabricated, and regulatory and functional
testing of the packages, transport trailer, and the auxiliary
handling and tiedown equipment have been completed. Fluor
Fernald has conducted a bidding process for the manufacturing
of waste packages, and begun award of contracts for fabrication
of the production packages. Next, the bidding process will
begin for supplying the trailers and tiedown equipment and
for actual transportation of the packages to the disposal
site.
|