Current Issues
Environmental

Duke Energy is subject to international, federal, state and local regulations regarding air and water quality, hazardous and solid waste disposal and other environmental matters.

Manufactured Gas Plants and Superfund Sites. Duke Energy was an operator of manufactured gas plants until the early 1950s and has entered into a cooperative effort with the State of North Carolina and other owners of certain former manufactured gas plant sites to investigate and, where necessary, remediate these contaminated sites. The State of South Carolina has expressed interest in entering into a similar arrangement. Duke Energy is considered by regulators to be a potentially responsible party and may be subject to future liability at seven federal Superfund sites and three state Superfund sites. While the cost of remediation of the remaining sites may be substantial, Duke Energy will share in any liability associated with remediation of contamination at such sites with other potentially responsible parties. Management believes that resolution of these matters will not have a material adverse effect on consolidated results of operations or financial position.

PCB (Polychlorinated Biphenyl) Assessment and Clean-up Programs. TETCO, a wholly owned subsidiary of Duke Energy, is currently conducting PCB assessment and clean-up programs at certain of its compressor station sites under conditions stipulated by a U.S. Consent Decree. The programs include on- and off-site assessment, installation of on-site source control equipment and groundwater monitoring wells, and on- and off-site clean-up work. TETCO completed the soil clean-up programs during 1998, subject to regulatory approval. Groundwater monitoring activities will continue at several sites beyond 1999.

In 1987, the Commonwealth of Kentucky instituted a suit in state court against TETCO, alleging improper disposal of PCBs at TETCO's three compressor station sites in Kentucky. This suit is still pending. In 1996, TETCO completed clean-up of these sites under the U.S. Consent Decree.

Duke Energy has also identified environmental contamination at certain sites on the PEPL and Trunkline systems and has undertaken clean-up programs at these sites. The contamination resulted from the past use of lubricants containing PCBs and the prior use of wastewater collection facilities and other on-site disposal areas. Soil and sediment testing, to date, has detected no significant off-site contamination. Duke Energy has communicated with the Environmental Protection Agency (EPA) and appropriate state regulatory agencies on these matters. Under the terms of the agreement with CMS Energy Corporation, Duke Energy is obligated to complete the PEPL and Trunkline clean-up programs at certain agreed-upon sites. These clean-up programs are expected to continue until 2001.

At December 31, 1998 and 1997, remaining estimated clean-up costs on the TETCO, PEPL and Trunkline systems were accrued and included in the Consolidated Balance Sheets as Environmental Clean-up Liabilities. These cost estimates represent gross clean-up costs expected to be incurred, have not been discounted or reduced by customer recoveries and generally do not include fines, penalties or third-party claims. Costs expected to be recovered from customers have been deferred and are included in the Consolidated Balance Sheets as Environmental Clean-up Costs.

The federal and state clean-up programs are not expected to interrupt or diminish Duke Energy's ability to deliver natural gas to customers. Based on Duke Energy's experience to date and costs incurred for clean-up operations, management believes the resolution of matters relating to the environmental issues discussed above will not have a material adverse effect on consolidated results of operations or financial position.

Air Quality Control. The Clean Air Act Amendments of 1990 require a two-phase reduction by electric utilities in aggregate annual emissions of sulfur dioxide and nitrogen oxide by 2000. Duke Energy currently meets all requirements of Phase I. Duke Energy supports the national objective of protecting air quality in the most cost-effective manner, and has already reduced emissions by operating plants efficiently, using nuclear and hydroelectric generation and implementing various compliance strategies. To meet Phase II requirements by 2000, Duke Energy's current strategy includes using low-sulfur coal, purchasing sulfur dioxide emission allowances and installing low-nitrogen oxide burners and emission monitoring equipment. Construction activities needed to comply with Phase II requirements are substantially complete. Additional annual operating expenses of approximately $25 million for low-sulfur coal premiums, emission allowance purchases and other compliance activities will occur after 2000. This strategy is contingent upon developments in future markets for emission allowances, low-sulfur coal, future regulatory and legislative actions and advances in clean air technologies.

In October 1998, the EPA issued a final ruling on regional ozone control which requires revised State Implementation Plans for 22 eastern states and the District of Columbia. This EPA ruling is being challenged in court by various states, industry and other interests, including the states of North Carolina and South Carolina and Duke Energy. Depending on the resolution of this matter, costs to Duke Energy may range from approximately $100 million to $500 million.

In December 1997, the United Nations held negotiations in Kyoto, Japan to determine how to achieve worldwide stabilization of greenhouse gas emissions, including carbon dioxide emissions from fossil-fired generating facilities and methane from natural gas operations. Further negotiations in November 1998 in Buenos Aires, Argentina, resulted in a work plan to complete the operational details of the Kyoto agreement by late 2000. Duke Energy is taking steps to prepare for possible action on greenhouse gas emissions and has completed a greenhouse gas emissions inventory. Implications of greenhouse gas emissions are being integrated into planning processes. Because this matter is in the early stages of discussion, management cannot estimate the effects on future consolidated results of operations or financial position.